CNC machining lead time
A quoted lead time is usually the machining time. The real date includes material, finishing, inspection and freight, and each has its own queue that the machining quote does not show.
Send a drawingThe six stages
Every stage has a normal duration and a set of things that stretch it. Knowing which stage your part will sit in is how you plan a launch date rather than hope.
| Stage | Typical | What stretches it |
|---|---|---|
| Drawing review and quote | 1 day | Unclear tolerance, missing alloy |
| Material procurement | 2-5 days | Non-stock alloy or thickness |
| Machining | 3-7 days | Fixture build, thin walls, tight tolerance |
| Finishing | 3-7 days | Anodizing queue, colour matching |
| Inspection | 1-2 days | FAI, CMM on many features |
| Freight | 3-5 days air / 25-35 sea | Port congestion, customs |
What actually compresses it
A complete drawing package saves three days of questions. Stock material saves a week. Skipping anodizing saves another week if the part does not need it.
The cheapest way to a shorter lead time is not pressure on the shop; it is removing a stage from the route.
What stretches it without warning
A first article that fails and needs a setup change; a colour sample that is rejected; a coating that has to be stripped and redone. Each adds a cycle, and each is more likely on a part that was rushed into production.
For repeat orders the route is proven, which is why the second order is usually two to five days faster than the first.
| Situation | Added time | Avoid by |
|---|---|---|
| Non-stock material | +5-15 days | Specify a stock grade |
| Failed first article | +2-5 days | Drawing review before cutting |
| Colour rejection | +5-7 days | Approve a sample first |
| Third-party inspection | +2-4 days | Book it when you order |
| Custom packing | +1-3 days | Specify packing with the order |
How to plan a launch
Work backwards from the date you need parts in hand: 30-35 days for sea freight, 5-8 for air. Then add finishing, inspection, machining and material in that order.
A prototype and a production run scheduled against the same date will collide at the machines. Stagger them, or expect the prototype to be late.
FAQ
- How long does CNC machining take?
- Three to seven working days for most parts once material is in and the drawing is agreed, plus finishing and freight.
- Why is the first order slower?
- No proven program or fixture, a first article to pass, and often a colour sample to approve.
- Can you expedite?
- Sometimes, by re-sequencing the machines. It is worth asking before the order rather than after the deadline has passed.
Have a drawing to review?
Send the model, the revision and the quantity. You get a written review of the open items with the price.